October 2021

Things are certainly looking very different on-site at The Bottleworks, with demolition works now complete.

We are excited to share this great shot by a local drone operator capturing the fantastic work by the demolition team removing the non-heritage elements of the former Big Shed so that only the 1920s Glassworks building remains.

Civil construction commenced last month with the external sewer approaching completion and external drainage works half completed. The external watermain works are due to commence shortly.

Unfortunately, due to COVID lockdown restrictions, the project has experienced some construction delays. Hygge Property and the project team are working very hard to manage the delays and bring the project back onto programme.